As you may know, work is being carried out to repair and reinforce the wall at 13 – 15 Park Winding. A visual inspection of the wall stem reinforcement was carried out by G3 Consulting Engineers, prior to concrete pour.

Description of Observations:
All formwork was in place and reinforcement complete at the time of the site visit.
The formwork installation is neat and tidy.
The stem reinforcement is neat and tidy, with appropriate laps and spacers.
Provision is in place for steps in top of wall and for weep holes per the drawings.

Below are photographs taken by G3 consulting Engineers, showing the extent of the work being carried out.